Watercourse Proj. City Project Homes Sq.Ft. Dist. Estimated Linear Cost/ Project Avg. Rank
(Watershed Identifier) # Ward Description Protect HDLU Rip. Project Feet Sq.Ft. Cost/ Total
(See below) Protect (acre) Cost Struc. Linear Score
Foot
Arroyo Chico (CW) 12 6 OC/C, STR 86 250000 --- $640,000 2770 $2 $231 99.6 1 Arroyo Chico (CW) 13 6 OC/V, STR 113 --- --- $831,000 5600 $5 $148 98.2 2 18th Street Wash (CL) 11 5 DET/RET 21 133500 --- $470,000 NA $3 NA 96.4 3 Mission View Wash (CC) 10 5 DET/RET 44 23500 1.6 $910,000 NA $11 NA 92.1 4 Citation Wash (CW) 15 5 OC/C, CBC 29 87000 --- $353,000 5000 $3 $71 89.9 5 Nebraska Wash (AW) 7 1,5 SD 52 33600 --- $1,466,000 4800 $14 $305 87.6 6 El Vado Wash (AG) 2 1 OC/SC, CBC 80 --- --- $1,336,000 4400 $12 $304 87.4 7 Railroad Wash (CW) 21 5 OC/E 13 --- --- $80,000 1600 $4 $50 86.9 8 Naylor Wash (CW) 20 4 OC/C 67 50000 --- $356,000 3940 $2 $90 85.7 9 Tucson Gen Wash (GM) 36 3 DET/RET 3 847800 --- $3,163,000 NA $4 NA 85.2 10 High School Wash (CW) 18 6 Replace CLVT --- --- --- $1,004,000 NA NA NA 85.1 11 Santa Clara Wash (AH) 4 1 OC/CC, CBC 52 --- --- $833,000 3400 $11 $245 84.4 12 Alamo Wash (GC) 32 2,6 SD 184 10000 --- $3,523,000 14820 $13 $238 84.2 13 Wilson Wash (DG) 27 3 SD 258 210000 --- $3,525,000 8030 $6 $439 84.1 14 Airport Wash (AW) 8 1,5 OC/CC, CBC 36 23400 2.9 $2,635,000 3750 $36 $703 83.6 15 Navajo Wash (DG) 28 3 SD 135 528900 --- $4,066,000 6360 $6 $639 82.9 16 Naylor Wash (CW) 19 5 OC/C, CBC 55 --- --- $1,672,000 9200 $22 $182 81.3 17 Fahringer Wash (MN) 44 2 STR 18 --- --- $101,000 3300 $4 $31 80.9 18 Citation Wash (CW) 14 6 OC/C, CBC 63 80000 --- $817,000 3440 $5 $238 80.3 19 Rodeo Wash (BR) 9 1,5 CBC (4) 13 600 --- $1,904,000 NA $101 NA 80.1 20 Christmas Wash (GL) 33 3 OC/V, CBC(3) 12 --- 1.1 $1,420,000 2000 $85 $710 79.7 21 Alamo Wash (GC) 31 2 ,4,6 CBC (7) --- --- --- $477,000 NA NA NA 79.3 22 Krueger Wash (DF) 26 3 OC/E, CBC --- 347200 --- $211,000 1200 $1 $176 78.9 23 Christmas Wash (GL) 34 3 OC/SC 24 --- --- $602,000 1200 $18 $502 77.3 24 Silverlake Wash (CW) 22 5 OC/C, CBC 45 --- --- $406,000 3960 $6 $103 76.8 25 Wetmore Wash (HR) 42 3 SD 42 22000 --- $1,520,000 2400 $19 $633 76.5 26 Christmas Wash (GL) 35 3 SD 222 --- --- $3,747,000 3000 $12 $1,249 76.1 27 Cemetery Wash (DG) 29 3 SD 48 68260 --- $936,000 4050 $7 $231 76.1 28 West University (DA) 24 1 SD 6 11250 --- $811,000 2600 $41 $312 75.8 29 North Mountain Ave (GQ) 37 3 SD 31 --- --- $812,000 3300 $19 $246 75.6 30 El Vado Wash (AG) 3 1 SD, STR 26 --- --- $1,730,000 1300 $48 $1,331 75.6 31 High School Wash (CW) 17 6 Modify CLVT 10 7000 --- $237,000 NA $11 NA 75.0 32 North Mountain Ave (GQ) 38 3 OC/SC, CBC 2 --- --- $762,000 1600 $272 $476 74.0 33 Hidden Hills Wash (MR) 45 2 OC/C 20 --- --- $1,471,000 4472 $53 $329 74.0 34 Bronx Wash (DC) 25 3,6 OC/C 17 112775 --- $621,000 2320 $5 $268 73.6 35 Fahringer Wash (MN) 43 2 OC/G-R 4 --- 3 $995,000 2200 $178 $452 72.8 36 First Avenue Wash (GR) 39 3 SD 13 4025 --- $1,110,000 3420 $50 $325 71.9 37 El Vado Wash (AG) 1 1 SD --- --- --- $1,027,000 2200 NA $467 71.7 38 Rolling Hills Wash (UC) 47 2,4 OC/C, CBC 23 --- --- $995,000 2400 $31 $415 71.5 39 Swan Park Wash (CW) 23 5 OC/C, CBC 14 --- --- $230,000 2640 $12 $87 71.2 40 Robb Wash (MW) 46 2 OC/C, OC/G 33 --- 1.5 $914,000 1800 $20 $508 71.0 41 Stone Avenue Wash (HG) 41 3 SD 47 --- --- $795,000 2200 $12 $361 70.7 42 High School Wash (CW) 16 6 SD --- --- --- $1,521,000 2150 NA $707 69.8 43 Flowing Wells Wash (DG)*30 1 CBC --- --- --- $110,000 NA NA NA 69.6 44 Valencia Wash (AL) 5 1 SD 4 --- --- $818,000 1250 $146 $654 60.9 45 Valencia Wash (AL) 6 1 SD 6 2600 --- $1,527,000 2500 $139 $611 60.6 46 Racetrack Wash (GW) 40 3 OC/SC --- --- --- $598,000 1700 NA $352 57.1 47
Project Abbreviations:
OC/SC = Open Channel with Soil Cement Bank Protection
OC/V-E = Open Channel with Vegetative or Earthen Banks
OC/C = Open Channel with Concrete Lining
OC/G-R = Open Channel with Gabion or Riprap Banks
OC/CC = Open Channel, Compound (low-flow bank protection)
SD = Storm Drain
CBC = Concrete Box Culvert
STR = Street Improvements
DET/RET = Detention/Retention Facilities
CLVT = culverts
HDLU = Structures in high density land use categories
* = For Breakout Flow into Ruthrauff Road Watershed (EG)
Priority Rankings were determined by Stormwater CIP Prioritization Committee
and were based on the average scores of the following seven factors:
(1) Reduces dangers to human life, public health, and safety
(2) Reduces flood damages to residences, businesses, and public works
(3) Increase in Level of Service
(4) Overall cost effectiveness (benefits vs. costs)
(5) Multi-purpose uses (open space, trails, parks)
(6) Compatibility with water quality goals and objectives
(7) Overall public and political acceptability